Completed Projects

  Name and location Description Completion year Client
RUB at Muzaffarnagar Km 55
Muzaffarnagar

Construction of two lane Road Over Bridge in lieu of level crossing No. 55 at km 123/5-6 near Muzaffarnagar Railway station along with other allied work on Meerut Cantt-Saharanpur section

2016
Northern Railway
RUB at Sonipat Km 28 & 31
Sonipat

Work  of Construction of 2 Nos. Limited Height Subway of sizes 5.50 x 4.00 meter each (By cut 7 Cover method) to eliminate level crossing No.28 at km 45/9-11 and level crossing No.31 at Km 48/9-11 between Sonepat-Sandalkalan on Delhi-Ambala section of Northern Railway

2016
Northern Railway
Periphery Exteren Expressway
Dasna, Ghaziabad

COnstruction of Road Over Bridge at Km 46 to Km 71 along Eastern Phripheral Expressway (NH-NE II) 

2018
NHAI